Your Contractor Wants Half Up Front. Ontario Says That’s a Problem

Two quotes are sitting on your kitchen table. One runs to eleven pages and comes to $71,000. The other fits on a single sheet, comes to $58,000, and asks for fifty percent on signing.

Most people read that gap as a price difference. Usually it isn't. It's a difference in how much of the job has actually been thought through, and the payment schedule is where that shows up first.

The Deposit Tells You More Than the Price Does

A deposit covers materials ordered on your behalf and holds a slot in a schedule. It is not working capital for somebody else's unfinished basement. Ontario's own guidance to the trade is direct about this: the province's guide for home renovation businesses advises keeping deposits to no more than ten percent of the total project cost.

Ten percent isn't a statute. It's a norm, which is exactly what makes it useful, because deviations from a norm mean something. A contractor who wants half the contract value before a single sheet of drywall comes down is telling you about their cash position, and none of that is your problem until you fund it.

The opposite extreme deserves a look too. If a quote includes full custom millwork and asks for nothing up front, ask who's carrying that cost. Somebody is.

An Estimate Is a Commitment, Not a Guess

Here's the provision almost no homeowner knows about. In Ontario, when a written estimate forms part of a renovation contract, the contractor cannot charge more than ten percent above that estimate unless you've approved the additional work in writing. That's the Consumer Protection Act, not a courtesy.

It should change how you read a low number. A vague estimate isn't a bargain. It's a document the contractor has every incentive to keep vague, because specificity binds them. The eleven-page quote is harder to read and much harder to escape.

The Ten Days You Probably Don’t Know You Have

Renovation contracts signed at your kitchen table are, in most cases, direct agreements under Ontario law. That gives you ten days from receiving your written copy to cancel without penalty and without giving a reason. Deposits come back within fifteen days, less reasonable payment for any work already done.

Reputable firms know this and build around it. They'd rather you use the window and stay than skip it and resent the contract in week six. If someone pushes you to sign tonight for a price that expires at midnight, the pressure itself is the information.

Progress Payments Should Follow Work, Not the Calendar

The single most useful change you can make to a payment schedule is tying every draw to a completed, verifiable milestone instead of a date. Rough-in inspection passed. Cabinets installed and levelled. Tile complete and grouted. Deficiency list cleared.

Dates reward presence. Milestones reward progress. The difference sounds academic until week five, when a crew has been on site every day and nothing measurable has happened.

Hold something back, too: a meaningful final payment released only after the walkthrough and the deficiency list are genuinely closed. It's the only leverage you have at the exact moment you need it, and a contractor confident in their finishing will agree to it without much discussion.

Change Orders Are Where Budgets Actually Die

Almost no renovation ends at the contract price, and that isn't always a failure. You open a wall, find knob-and-tube, and now there's real work nobody could have priced blind.

What separates a managed overrun from a runaway one is paperwork. Ontario's guidance is clear that mid-project changes should be documented in writing, showing the effect on both price and timeline, and signed by both parties before the work proceeds. A verbal "yeah, we can do that" in a dusty hallway is how a $60,000 project becomes an $84,000 project, one small yes at a time.

See Also

Ask, before you sign, how change orders will be handled. The answer should involve a form and a signature, not a handshake.

Reading Two Quotes That Aren’t the Same Quote

Comparing renovation prices only means something when the scope underneath them matches, and it almost never does. One quote includes permit fees, disposal bins, protection of adjacent rooms and a licensed electrician. The other assumes you'll handle the city and quietly omits the bin.

Build a line-by-line comparison before you look at the totals. Demolition and disposal. Permits and inspections. Electrical and plumbing, including any code upgrades the work triggers. Materials, with a stated allowance for anything not yet selected. Finishing and cleanup. Warranty.

Anything missing from one quote isn't free. It's unpriced, and you'll pay for it later at worse rates. That's the reasoning behind fixed-scope proposals issued before work begins, the approach taken with home remodelling by renoWOW! and other established GTA firms that would rather argue about scope in week zero than bill for it in week nine.

The Contract Is the Product

You aren't buying tile and cabinets. You're buying somebody's ability to organise thirty deliveries, six trades and a city inspector into an order that doesn't collapse. The contract is the only evidence of that ability you get before the work starts.

So read the payment schedule first. It will tell you, more honestly than the price ever could, how the next four months are going to go.